Drilling in an Aluminium Rolling Mill

 Drilling in an Aluminium Rolling Mill image
Cable Tool Drilling Rig inside the Aluminium Rolling Mill
 

Overview

The challenge for this project was to complete 30 boreholes (135 metres) within a 72 hour period within a sensitive environment. The whole project was completed within a holiday weekend causing no disruption to the production of the mill. It was critical that the aluminium rolls located at the mill were not contaminated during this investigation.

Despite a late increase to the scope of the works, Land-Drill was able to complete the works on time.

Problem

Timescale:72 hours


 

Please review our Case Studies for further information.